There is described a method for conducting a subsea well intervention at a subsea well, and a related system. In particular embodiments, an assembly is provided comprising a wireline drum pressure container unit, a lubricator package having a lock chamber tube enclosing a tool string and having at least one valve in a vertical bore, and a connector used to connect the assembly to a well control package on a well head of the well. In such an embodiment, the method can include displacing well fluid in a cavity between the valve of the lubricator package and a valve of the well control package, using a clean fluid, while the valve of the lubricator package is closed. The assembly can then be disconnected from said well control package at the connector and retrieved to the surface, whereby contamination of seawater due to disconnection can be reduced or minimized.
E21B 33/072 - Têtes de puitsLeur mise en place comportant des dispositions pour introduire des objets dans les puits ou pour les en retirer, ou pour y introduire des fluides pour les outils manœuvrés par câbles
E21B 33/076 - Têtes de puitsLeur mise en place comportant des dispositions pour introduire des objets dans les puits ou pour les en retirer, ou pour y introduire des fluides spécialement adaptés aux installations sous l'eau
E21B 47/10 - Localisation des fuites, intrusions ou mouvements du fluide
A petroleum well intervention winch system includes a high pressure confining housing for a drum for a rope to a tool string. The pressure confining housing has a connector with an aperture for the rope to a top of a tool string gate chamber on vertical bore BOP valves on a wellhead on the petroleum well. The rope runs through the aperture via a capstan to the drum. The capstan is driven by a first motor through a first high pressure proof magnetic coupling across a wall of the housing. The drum is driven by a second motor through a second high pressure proof magnetic coupling across the wall of the housing. The capstan is subject to a load tension from the rope and is provided with a hold tension on the rope from the drum. The second motor exerts a constant hold tension on the rope via the drum.
E21B 23/14 - Appareils pour déplacer, mettre en place, verrouiller, libérer ou retirer, les outils, les packers ou autres éléments dans les trous de forage pour déplacer un câble ou un outil manœuvré par câble, p. ex. pour les opérations de diagraphie ou de perforation dans les puits déviés
E21B 41/00 - Matériel ou accessoires non couverts par les groupes
E21B 41/06 - Enceintes de travail pour opérations sous l'eau, p. ex. reliées temporairement aux têtes de puits
E21B 47/12 - Moyens pour la transmission de signaux de mesure ou signaux de commande du puits vers la surface, ou de la surface vers le puits, p. ex. pour la diagraphie pendant le forage
E21B 19/00 - Manipulation de tiges, tubages, tubes ou autre objets analogues à l'extérieur du trou de forage, p. ex. dans la tour de forageAppareils pour faire avancer les tiges ou les câbles
E21B 33/037 - Enceintes protectrices pour têtes de puits
E21B 33/076 - Têtes de puitsLeur mise en place comportant des dispositions pour introduire des objets dans les puits ou pour les en retirer, ou pour y introduire des fluides spécialement adaptés aux installations sous l'eau
A petroleum well intervention winch system comprising a high pressure confining housing (1) for a drum (2) for a rope (R) to a tool string (T), characterized by said pressure confining housing (1) having a connector (C) with an aperture (A) for said rope (R) to a top of a tool string gate chamber (G) on vertical bore BOP valves on a wellhead (WH) on said petroleum well, said rope from said tool string (T) running through said aperture (A) via a capstan (3) to said drum (2), said capstan (3) driven by a first motor (35) through a first high pressure proof magnetic coupling (34) across a wall of said housing (1), said drum (2) driven by a second motor (25) through a second high pressure proof magnetic coupling (24) across said wall of said housing (1), said capstan (3) subject to a load tension from said rope (R) from said tool string (T) in said well and provided with a hold tension on said rope (R) from said drum (2), said second motor (25) exerting a constant hold tension on rope (R) via drum (2).
E21B 33/037 - Enceintes protectrices pour têtes de puits
E21B 33/076 - Têtes de puitsLeur mise en place comportant des dispositions pour introduire des objets dans les puits ou pour les en retirer, ou pour y introduire des fluides spécialement adaptés aux installations sous l'eau
E21B 41/00 - Matériel ou accessoires non couverts par les groupes
E21B 41/06 - Enceintes de travail pour opérations sous l'eau, p. ex. reliées temporairement aux têtes de puits
E21B 47/12 - Moyens pour la transmission de signaux de mesure ou signaux de commande du puits vers la surface, ou de la surface vers le puits, p. ex. pour la diagraphie pendant le forage
B66D 1/00 - Mécanismes d'enroulement des cordes, câbles ou chaînesCabestans
E21B 19/00 - Manipulation de tiges, tubages, tubes ou autre objets analogues à l'extérieur du trou de forage, p. ex. dans la tour de forageAppareils pour faire avancer les tiges ou les câbles